FREE PMP Exam

PMP® Prep Exam Questions, PMBOK® Guide 6th Edition

You have 25 minutes to pass the test


Try PMP Exam

20 Prep Questions for the PMP® Exam, PMBOK® Guide 6th Edition

PMBOK Guide 6th Edition, Procurement Management PMP Exam

1 / 20

In many projects, negotiation is:

PMBOK Guide 6th Edition, Scope Management PMP Exam

2 / 20

... describe capabilities that are temporary and are no longer needed after the new product/service/result is ready.

PMBOK Guide 6th Edition, Resource Management PMP Exam

3 / 20

Generally acknowledged techniques for resolving conflict include:

PMBOK Guide 6th Edition, Risk Management PMP Exam

4 / 20

The Perform Qualitative Risk Analysis process assesses the priority of identified risks using all of the following, EXCEPT:

PMBOK Guide 6th Edition, Procurement Management PMP Exam

5 / 20

The buyer, usually through its authorized procurement administrator, provides the seller with ... as an output of the Control Procurement process.

PMBOK Guide 6th Edition, Risk Management PMP Exam

6 / 20

As an output of the Monitor Risks process, an updated risk register generally includes some or all of the following, EXCEPT:

PMBOK Guide 6th Edition, Communications Management PMP Exam

7 / 20

Hard-copy document management, electronic communications management, and web interfaces to scheduling and project management software are examples of:

PMBOK Guide 6th Edition, Introduction PMP Exam

8 / 20

All of the following are true about projects and operations, EXCEPT:

PMBOK Guide 6th Edition, Procurement Management PMP Exam

9 / 20

Approved change requests can generally include all of the following, EXCEPT:

PMBOK Guide 6th Edition, Procurement Management PMP Exam

10 / 20

All of the following are inputs to the Plan Procurement Management process, EXCEPT:

PMBOK Guide 6th Edition, Scope Management PMP Exam

11 / 20

Which of the following statements is true about the work breakdown structure (WBS)?

PMBOK Guide 6th Edition, Resource Management PMP Exam

12 / 20

Team development stages include:

PMBOK Guide 6th Edition, Scope Management PMP Exam

13 / 20

All of the following are true about the Control Scope process, EXCEPT:

PMBOK Guide 6th Edition, Integration Management PMP Exam

14 / 20

Outputs of the Monitor and Control Project Work process include all of the following EXCEPT:

PMBOK Guide 6th Edition, Integration Management PMP Exam

15 / 20

All of the following are characteristics of the Project Management Information System (PMIS), EXCEPT:

PMBOK Guide 6th Edition, Schedule Management PMP Exam

16 / 20

Three-point estimating uses:

PMBOK Guide 6th Edition, Tailoring Considerations PMP Exam

17 / 20

The types and quantities of resources required for each activity in a work package.

PMBOK Guide 6th Edition, Agile Practice PMP Exam

18 / 20

All of the following are Process Groups in adaptive environments, EXCEPT:

PMBOK Guide 6th Edition, Quality Management PMP Exam

19 / 20

Manage quality is the process of:

PMBOK Guide 6th Edition, Introduction PMP Exam

20 / 20

A significant amount of data is collected and analyzed throughout the project. All of the following are examples of project data and information, EXCEPT:

Access Only For PMboard Members


Locked Exam

Free PMP Exam

50 Prep Questions for the PMP® Exam, PMBOK® Guide 6th Edition

Access Only For PMboard Members


Locked Exam

Free PMP Exam

100 Prep Questions for the PMP® Exam, PMBOK® Guide 6th Edition

Access Only For PMboard Members


Locked Exam

Free PMP Exam

200 Prep Questions for the PMP® Exam, PMBOK® Guide 6th Edition

PMboard Associate CAPM Exam Logo
5 11 votes
Article Rating
guest
0 Comments
Most Voted
Newest Oldest
Inline Feedbacks
View all comments