FREE PMP Exam

PMP® Prep Exam Questions, PMBOK® Guide 6th Edition

You have 25 minutes to pass the test


Try PMP Exam

20 Prep Questions for the PMP® Exam, PMBOK® Guide 6th Edition

PMBOK Guide 6th Edition, Resource Management PMP Exam

1 / 20

It is important that the resource management plan addresses how team members will be released when they are no longer needed on the project for all of the following reasons, EXCEPT:

PMBOK Guide 6th Edition, Scope Management PMP Exam

2 / 20

An output of the Define Scope process is:

PMBOK Guide 6th Edition, Project Environment PMP Exam

3 / 20

Governance is the framework within which authority is exercised in organizations. This framework includes all of the following components, EXCEPT:

PMBOK Guide 6th Edition, Cost Management PMP Exam

4 / 20

An activity cost estimate includes all of the following resource categories, EXCEPT:

PMBOK Guide 6th Edition, Resource Management PMP Exam

5 / 20

Generally acknowledged techniques for resolving conflict include:

PMBOK Guide 6th Edition, Key Concepts PMP Exam

6 / 20

Project Risk Management includes all of the following, EXCEPT:

PMBOK Guide 6th Edition, Schedule Management PMP Exam

7 / 20

Consider the following information about the duration of an activity: Calculated expected (tE)= 5 weeks. Optimistic (tO)= 4 weeks. Pessimistic (tP)= 8 weeks. Using the beta distribution and the three-point estimating approach, the Most likely (tM) activity duration is:

PMBOK Guide 6th Edition, Tailoring Considerations PMP Exam

8 / 20

For smaller projects, what is the supporting documentation that could be used to support the details used in establishing project estimates such as assumptions, constraints, level of detail, ranges, and confidence levels?

PMBOK Guide 6th Edition, Resource Management PMP Exam

9 / 20

All of the following choices represent inputs to the Estimate Activity Resources process, EXCEPT:

PMBOK Guide 6th Edition, Tailoring Considerations PMP Exam

10 / 20

What is a work breakdown structure (WBS)?

PMBOK Guide 6th Edition, Stakeholder Management PMP Exam

11 / 20

You are involved in the process of communicating and working with stakeholders to meet their needs/expectations, address issues as they occur, and foster appropriate stakeholder engagement in project activities throughout the project life cycle. This is known as:

PMBOK Guide 6th Edition, Tailoring Considerations PMP Exam

12 / 20

When tailoring processes for Project Quality Management, you should consider all of these, EXCEPT:

PMBOK Guide 6th Edition, Quality Management PMP Exam

13 / 20

Control charts have all of the following characteristics, EXCEPT:

PMBOK Guide 6th Edition, Resource Management PMP Exam

14 / 20

The Responsibility Assignment Matrix (RAM) is:

PMBOK Guide 6th Edition, Risk Management PMP Exam

15 / 20

Risk transference nearly always involves:

PMBOK Guide 6th Edition, Cost Management PMP Exam

16 / 20

The cost management plan has all of the following characteristics, EXCEPT:

PMBOK Guide 6th Edition, Tailoring Considerations PMP Exam

17 / 20

Tom, a project manager of a large defense project, is using a technique for estimating the duration of an activity in his project using historical data from a similar activity or project.

PMBOK Guide 6th Edition, Procurement Management PMP Exam

18 / 20

All of the following are inputs to the Plan Procurement Management process, EXCEPT:

PMBOK Guide 6th Edition, Tailoring Considerations PMP Exam

19 / 20

When tailoring processes for Project Risk Management, you should consider all of these, EXCEPT:

PMBOK Guide 6th Edition, Integration Management PMP Exam

20 / 20

Some of the configuration management activities included in the Perform Integrated Change Control process include all of the following activities, EXCEPT:

Access Only For PMboard Members


Locked Exam

Free PMP Exam

50 Prep Questions for the PMP® Exam, PMBOK® Guide 6th Edition

Access Only For PMboard Members


Locked Exam

Free PMP Exam

100 Prep Questions for the PMP® Exam, PMBOK® Guide 6th Edition

Access Only For PMboard Members


Locked Exam

Free PMP Exam

200 Prep Questions for the PMP® Exam, PMBOK® Guide 6th Edition

PMboard Associate CAPM Exam Logo
5 11 votes
Article Rating
guest
0 Comments
Most Voted
Newest Oldest
Inline Feedbacks
View all comments