FREE PMP Exam

PMP® Prep Exam Questions, PMBOK® Guide 6th Edition

You have 25 minutes to pass the test


Try PMP Exam

20 Prep Questions for the PMP® Exam, PMBOK® Guide 6th Edition

PMBOK Guide 6th Edition, Schedule Management PMP Exam

1 / 20

Analogous duration estimating is:

PMBOK Guide 6th Edition, Quality Management PMP Exam

2 / 20

The basis for continuous quality improvement is the:

PMBOK Guide 6th Edition, Cost Management PMP Exam

3 / 20

Earned value management (EVM) is a commonly used:

PMBOK Guide 6th Edition, Tailoring Considerations PMP Exam

4 / 20

Select the answer that BEST describes test and evaluation documents:

PMBOK Guide 6th Edition, Procurement Management PMP Exam

5 / 20

The buyer structures procurement documents, which include all of the following, EXCEPT:

PMBOK Guide 6th Edition, Integration Management PMP Exam

6 / 20

You are managing a $10 million project. Which of the following is an acceptable cause for “re-baselining” this project?

PMBOK Guide 6th Edition, Resource Management PMP Exam

7 / 20

Acquire resources is the process of confirming resource availability and obtaining the team necessary to complete project activities. The enterprise environmental factors that can influence this process generally include all of the following, EXCEPT:

PMBOK Guide 6th Edition, Tailoring Considerations PMP Exam

8 / 20

Which of the below represents the BEST definition for quality audits?

PMBOK Guide 6th Edition, Tailoring Considerations PMP Exam

9 / 20

When tailoring processes for Project Cost Management, you should consider all of these, EXCEPT:

PMBOK Guide 6th Edition, Cost Management PMP Exam

10 / 20

All of the following are true about cost estimates, EXCEPT:

PMBOK Guide 6th Edition, Schedule Management PMP Exam

11 / 20

For project scheduling, bar charts show:

PMBOK Guide 6th Edition, Key Concepts PMP Exam

12 / 20

Project Resource Management includes all of the following, EXCEPT:

PMBOK Guide 6th Edition, Introduction PMP Exam

13 / 20

For a project to be successful, the project should generally achieve all of the following, EXCEPT:

PMBOK Guide 6th Edition, Tailoring Considerations PMP Exam

14 / 20

The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint.

PMBOK Guide 6th Edition, Schedule Management PMP Exam

15 / 20

The precedence diagramming method (PDM) is:

PMBOK Guide 6th Edition, Tailoring Considerations PMP Exam

16 / 20

When tailoring processes for Project Resource Management, you should consider all of these, EXCEPT:

PMBOK Guide 6th Edition, Stakeholder Management PMP Exam

17 / 20

Which of the following is NOT a process in Project Stakeholder Management?

PMBOK Guide 6th Edition, Tailoring Considerations PMP Exam

18 / 20

A documented economic feasibility study used to establish validity of the benefits of a selected component lacking sufficient definition and that is used as a basis for the authorization of further project management activities.

PMBOK Guide 6th Edition, Project Manager Role PMP Exam

19 / 20

Complexity exhibits all of the following characteristics, EXCEPT:

PMBOK Guide 6th Edition, Introduction PMP Exam

20 / 20

Project management is:

Access Only For PMboard Members


Locked Exam

Free PMP Exam

50 Prep Questions for the PMP® Exam, PMBOK® Guide 6th Edition

Access Only For PMboard Members


Locked Exam

Free PMP Exam

100 Prep Questions for the PMP® Exam, PMBOK® Guide 6th Edition

Access Only For PMboard Members


Locked Exam

Free PMP Exam

200 Prep Questions for the PMP® Exam, PMBOK® Guide 6th Edition

PMboard Associate CAPM Exam Logo
5 11 votes
Article Rating
guest
0 Comments
Inline Feedbacks
View all comments